            				  (ISO) Tank Containers
    
                   
                            
- Certificate of previous/last cargo in order to check the compability of the present cargo to be filed in case of any residuals are left.
 
- Copy of Cleanliness Certificate.
 
- Empty tank pressure check.
 
- Tanks after filling are checked externally for any damages, leakages at inlet/filling port and bottom outlet.
 
- Check T-number on Tank certification plate to verify the Tank meet the IMDG requirements to match the DG with the Tank.
 
- Seal check: to check if sealing has been carried out and note down the seal numbers.
 
- Every tank should be 80% full (to avoid surge), but less than 95% full (for thermal expansion).
 
- Placarding affixed to the containers as per IMDG requirement.
 
- Photography of the tank of the above process.
 
- Documents to be provided : BRO, SDS, Packing list